Campus additions to include expansion of the existing library, science classroom, computer lab, art classroom, and a teacher lounge. Campus renovations to include life cycle items, collaboration/makerspaces, and playground equipment.

KEY INFORMATION
Trustee
Anne Darr
Budget
$6,227,267
Opening Date
August 2021
Design Process
Address
3060 Overton Park Dr. W
Fort Worth, TX 76109
1,737
New Square Footage
10,000
Renovated Square Footage
Construction Process
PROJECT TEAM
Sample avatar
Matt Tanner
Matt Tanner
Owner Representative
Sample avatar
To Be Determined
To Be Determined
Contractor
Bennett Benner Partners
Architect

EMAIL UPDATES

Subscribe below to receive Tanglewood Elementary School email updates.
PROJECT UPDATES
Library Framing

09/04/2020

The new library addition is moving along quickly with the exterior framing complete. Next, the exterior sheathing will be installed.

Back to Demoing

08/21/2020

After completing the restrooms, demolition is now beginning in the music room and counseling room

Library Addition

08/14/2020

The library addition continues to make progress. The steel work began last week and will wrap up soon.

Restroom Renovations Near Completion

07/31/2020

The boys and girls restroom remodels are near completion with new tile installed and fixtures currently being set

Restroom Renovation

07/24/2020

The renovations in the restrooms continue to make progress. The tile install is ongoing, soon the fixtures will be installed.

Tiling Tanglewood

07/15/2020

The renovated restrooms’ tiles are being set!

Foundations

07/10/2020

The library grade beam pour is complete,  CMU blocks in the first-floor restroom are being installed, and the upstairs plumbing […]

Ready, Set, Rebar

07/03/2020

The grade beams at the new library addition are formed, and with the rebar set, we are ready for concrete […]

Working from Below

06/26/2020

The trenching for the new plumbing tie in has been made and rebar is set and ready for the concrete […]

Construction has Commenced!

06/12/2020

We have demoed the three sets of boys’ and girls’ restrooms, the exterior concrete for the new library addition, and […]