Southwest High School will receive a new Athletic Facility.
KEY INFORMATION
Trustee
CJ Evans
Budget
$3,199,390
Opening Date
February 2020
Design Process
Address
4100 Altamesa Blvd
Fort Worth, TX 76133
N/A
New Square Footage
N/A
Renovated Square Footage
Construction Process
PROJECT TEAM
Sample avatar
Matt Tanner
Matt Tanner
Owner Representative
Mac's Construction
Contractor
Parkhill Smith & Cooper
Architect

EMAIL UPDATES

Subscribe below to receive Southwest High School email updates.
PROJECT UPDATES
Nearly Picture Perfect

02/13/2020

We’re nearly complete with the final punch list! The last item on the list are the graphics which are going to be installed soon.

Shortening Our To-Do Lists

01/29/2020

The Mechanical, Electrical, and Plumbing (MEP) have been finalized! The few things that are left to be completed are the owner trainings and the exterior building graphics

Signed, Sealed, & (Almost) Delivered!

01/13/2020

The main hallway has been cleaned in order to be sealed (photo 1), the laundry room is waiting on the washer and dryer to be installed (photo 2), and lastly, the varsity football lockers are set! (photo 3)

Lights, Tiles, Action!

12/23/2019

The tile work is complete in the athletics building and the electrical and plumbing fixtures are wrapping up. Up next on the agenda is painting the hallways and staining the floors!

Interiors & Exteriors... Everything Matters!

12/11/2019

While the outdoors is being dressed with fencing and landscaping, the athletic facility main corridor is completely tiled.

Phasing Out of Phase 1

11/20/2019

Concrete for the sidewalks have been poured, the restroom tiles are complete, and the tiles for the locker room walls are being placed. Look out for phase 2 additions!

Sidewalks and Interior Work Progressing

11/07/2019

Sidewalks are being formed and poured (Photo 1). Interior window and door frames are installed (Photo 2). Contractors are working on above ceiling electrical (Photo 3) and concrete floor stain colors have been mocked up for review (Photo 4).

Interior Finishes Underway

10/31/2019

Hallways are in process of being painted and other walls prepared for tile installation. A window from hallway gives a peak into the coach’s office.

Interior Finish Out Continues

10/12/2019

HVAC work is on-going above the ceiling. Sheetrock is complete in various areas and ready for wall tile. Exterior finish is nearing completion.

Installations and more Installations

09/25/2019

Sheetrock and insulation is going in, along with the spiral duct and storm line being installed.

Framing and Insulation

08/29/2019

Construction is currently ongoing with the interior metal framing, exterior wall insulation wrapping up, and above ceiling MEP install.

Pre-Engineered Metal Building

08/08/2019

Exterior metal sheathing has been completed and contractor has begun the roof decking activities.

Prepping the pad

07/17/2019

The building pad is being prepped and cast iron plumbing is being installed in the ground under the slab.

A Look Inside

06/17/2019

Conceptual renderings showing what the interior of the new athletic facility will look like.

Rebar and Beams

06/14/2019

An overview look at building pad grade-beam forming. Re-setting grade-beam forms affected by the weather and the grade-beam rebar being completed.

A Glimpse

05/01/2019

Preliminary renderings give a glimpse of how the new athletic addition may appear.

Drilling for a foundation

04/23/2019

Drilling to prepare to lay out the foundation for the new athletic addition.

Pre-Proposal Meeting Recap

01/25/2019

A pre-proposal meeting was held for the bid opportunity, CSP-BP 19-040 Southwest HS Athletic Addition, where vendors found out more information about aspects of the procurement process, proposal requirements, contract time, budget and scope. To stay up to date on upcoming bid opportunities, please visit fwisd2017bond.com/vendors.

Bid Opportunity and Pre-Proposal Meeting

01/17/2019

A pre-proposal meeting will be held on Thursday, January 24th, at 2:00pm for the bid opportunity, CSP-BP 19-040 Southwest HS Athletic Addition. Find out more information by clicking here.

Elevation

11/16/2018

A visual of the elevation of the exterior of the Southwest HS Athletic Facility. It shows the exterior finish of the building and the patterns that will be incorporated.