Campus additions to include expansion of the existing library, science classroom, computer lab, art classroom, and a teacher lounge. Campus renovations to include life cycle items, collaboration/makerspaces, and playground equipment.

KEY INFORMATION
Trustee
Kevin Lynch
Budget
$6,227,267
Opening Date
September 2021
Design Process
Address
3060 Overton Park Dr. W
Fort Worth, TX 76109
1,737
New Square Footage
10,000
Renovated Square Footage
Construction Process
PROJECT TEAM
Sample avatar
Edsel Gaitonde
Edsel Gaitonde
Owner Representative
Sample avatar
Reeder
Reeder
Contractor
Bennett Benner Partners
Architect

EMAIL UPDATES

Subscribe below to receive Tanglewood Elementary School email updates.
PROJECT UPDATES

10/01/2021

The secure front entry vestibule and landscaping are complete!

Tanglewood is Complete!

10/01/2021

Tanglewood is Going Green!

08/13/2021

The landscaping is being planted!

Canopy Coming Along

08/06/2021

The front entry’s canopy is taking shape!

Front Entry Stairway

05/18/2021

The front stairway has been framed and poured!

Front Entry Progress

04/23/2021

Grade beam work has begun for the front entry!

Focusing on the Front Entry!

04/16/2021

The underground utility work, earthwork, and pier drilling have all taken place. Now time for the front entry’s concrete pour.

The Auditorium is Complete!

03/12/2021

New flooring, lighting and a stage renovation were the finishing touches on Tanglewood’s auditorium, making it ready for student performances […]

The Playground is Complete!

03/05/2021

The canopy has been installed, so the Tanglewood playground is now ready for the upcoming school year!

Playground Sneak-Peek!

02/05/2021

The playground equipment has been installed and awaiting the fall zone protection to be completed.

The New Library is Open

01/20/2021

The library is complete, providing a brightened new space for students to enjoy.  Temporary furniture is being used until the […]

Library Sneak Peek!

01/04/2021

Take a look at the new library addition!

Center Stage!

12/11/2020

Great progress has been made in the auditorium including the stage renovation and new pendent lighting over the seating area.

Working from the Ground Up

12/02/2020

The concrete has been poured for the new courtyard outside the media enter which will provide a place for outdoor […]

Library Update

10/16/2020

The masonry install and interior framing is ongoing at the new media center addition.  Large windows (shown in right photo) […]

A Few Finished Rooms

10/02/2020

The counselor rooms, teacher lounge, and music room have all been completed

Library Framing

09/04/2020

The new library addition is moving along quickly with the exterior framing complete. Next, the exterior sheathing will be installed.

Back to Demoing

08/21/2020

After completing the restrooms, demolition is now beginning in the music room and counseling room

Library Addition

08/14/2020

The library addition continues to make progress. The steel work began last week and will wrap up soon.

Restroom Renovations Near Completion

07/31/2020

The boys and girls restroom remodels are near completion with new tile installed and fixtures currently being set

Restroom Renovation

07/24/2020

The renovations in the restrooms continue to make progress. The tile install is ongoing, soon the fixtures will be installed.

Tiling Tanglewood

07/15/2020

The renovated restrooms’ tiles are being set!

Foundations

07/10/2020

The library grade beam pour is complete,  CMU blocks in the first-floor restroom are being installed, and the upstairs plumbing […]

Ready, Set, Rebar

07/03/2020

The grade beams at the new library addition are formed, and with the rebar set, we are ready for concrete […]

Working from Below

06/26/2020

The trenching for the new plumbing tie in has been made and rebar is set and ready for the concrete […]

Construction has Commenced!

06/12/2020

We have demoed the three sets of boys’ and girls’ restrooms, the exterior concrete for the new library addition, and […]