Southwest High School will receive a new Athletic Facility.
KEY INFORMATION
Trustee
Anne Darr
Budget
$3,199,390
Opening Date
February 2020
Design Process
Address
4100 Altamesa Blvd
Fort Worth, TX 76133
N/A
New Square Footage
N/A
Renovated Square Footage
Construction Process
PROJECT TEAM
Sample avatar
Stoney Crump
Stoney Crump
Owner Representative
Mac's Construction
Contractor
Parkhill Smith & Cooper
Architect

EMAIL UPDATES

Subscribe below to receive Southwest High School email updates.
PROJECT UPDATES
Raiders Ready!

04/10/2020

With the exterior graphic finished, the Southwest Athletics project is complete!

Locker Rooms Are Finished!

04/07/2020

Nearly Picture Perfect

02/13/2020

We’re nearly complete with the final punch list! The last item on the list are the graphics which are going […]

Shortening Our To-Do Lists

01/29/2020

The Mechanical, Electrical, and Plumbing (MEP) have been finalized! The few things that are left to be completed are the […]

Signed, Sealed, & (Almost) Delivered!

01/13/2020

The main hallway has been cleaned in order to be sealed (photo 1), the laundry room is waiting on the […]

Lights, Tiles, Action!

12/23/2019

The tile work is complete in the athletics building and the electrical and plumbing fixtures are wrapping up. Up next […]

Interiors & Exteriors... Everything Matters!

12/11/2019

While the outdoors is being dressed with fencing and landscaping, the athletic facility main corridor is completely tiled.

Phasing Out of Phase 1

11/20/2019

Concrete for the sidewalks have been poured, the restroom tiles are complete, and the tiles for the locker room walls […]

Sidewalks and Interior Work Progressing

11/07/2019

Sidewalks are being formed and poured (Photo 1). Interior window and door frames are installed (Photo 2). Contractors are working […]

Interior Finishes Underway

10/31/2019

Hallways are in process of being painted and other walls prepared for tile installation. A window from hallway gives a […]

Interior Finish Out Continues

10/12/2019

HVAC work is on-going above the ceiling. Sheetrock is complete in various areas and ready for wall tile. Exterior finish […]

Installations and more Installations

09/25/2019

Sheetrock and insulation is going in, along with the spiral duct and storm line being installed.

Framing and Insulation

08/29/2019

Construction is currently ongoing with the interior metal framing, exterior wall insulation wrapping up, and above ceiling MEP install.

Pre-Engineered Metal Building

08/08/2019

Exterior metal sheathing has been completed and contractor has begun the roof decking activities.

Prepping the pad

07/17/2019

The building pad is being prepped and cast iron plumbing is being installed in the ground under the slab.

A Look Inside

06/17/2019

Conceptual renderings showing what the interior of the new athletic facility will look like.

Rebar and Beams

06/14/2019

An overview look at building pad grade-beam forming. Re-setting grade-beam forms affected by the weather and the grade-beam rebar being […]

A Glimpse

05/01/2019

Preliminary renderings give a glimpse of how the new athletic addition may appear.

Drilling for a foundation

04/23/2019

Drilling to prepare to lay out the foundation for the new athletic addition.

Pre-Proposal Meeting Recap

01/25/2019

A pre-proposal meeting was held for the bid opportunity, CSP-BP 19-040 Southwest HS Athletic Addition, where vendors found out more […]

Bid Opportunity and Pre-Proposal Meeting

01/17/2019

A pre-proposal meeting will be held on Thursday, January 24th, at 2:00pm for the bid opportunity, CSP-BP 19-040 Southwest HS […]

Elevation

11/16/2018

A visual of the elevation of the exterior of the Southwest HS Athletic Facility. It shows the exterior finish of […]