South Hills High School will receive a new two-story classroom building.
Common spaces will be renovated to create collaboration spaces for learning and student interaction. Moderate renovations will be applied to various locations within the school to meet the twenty-first century learning model. Renovations will include reclaiming or repurposing space to support Career and Technical Education.
KEY INFORMATION
Trustee
Anne Darr
Budget
$52,628,735
Opening Date
May 2022
Design Process
Address
6101 McCart
Fort Worth, TX 76133
93,926
New Square Footage
60,000
Renovated Square Footage
Construction Process
PROJECT TEAM
Sample avatar
Garrett North
Garrett North
Owner Representative
Steele & Freeman
Contractor
Jacobs & Associates
Architect

EMAIL UPDATES

Subscribe below to receive South Hills High School email updates.
PROJECT UPDATES
Check out this Transformation!

01/03/2023

It’s safe to say the upgrades have completely changed the look of campus!

Interior Installations

03/28/2022

The lab casework has been installed in the science lab, and in the hallways the wall tile and the ceiling […]

Tile and Panel Installation

03/14/2022

The interior hexagonal wall tile is being installed, meanwhile, on the exterior, prep has begun for the Nichia panels.

Media Center Progress

02/21/2022

The furniture has been installed in the media center!

Windows & Flashing Installed!

02/07/2022

The windows and flashing have been installed. Take a look at the view looking up the stairs of exterior flashing […]

Addition & Media Center Progress

10/11/2021

The concrete curb and sidewalk near the entry of the new addition has been poured, meanwhile, carpet and tile are […]

Air Barrier Install

09/13/2021

The air barrier is being applied to the exterior sheathing

Entry Way & Building H Progress

09/02/2021

Brick is being installed at the front entrance, meanwhile, the building H’s interior framing is making progress

End of August Aerials

08/27/2021

From steel structures at the beginning of August, to ending August with the addition nearly completely framed!

Framing Has Begun

08/20/2021

Framing has begun at the addition!

Addition's First Floor

08/13/2021

The first floor and stairwell in the addition are taking shape!

August Aerials

08/02/2021

Beginning August by taking a look at the summer progress at South Hills!

Second Floor Steel

07/30/2021

Steel is going up for the addition’s second floor!

Renovation Update

07/23/2021

Poly and rebar have begun for the renovation of South Hills High School

Addition Taking Shape

07/09/2021

The addition’s interiors are taking shape!

Structural Steel Progress

06/25/2021

The addition’s structural steel has made great progress throughout the month of June.

Latest Installations

06/09/2021

The structural steel and decking are being installed… rain or shine!

New Addition Deck

04/23/2021

The topping slab on the hollow deck has been placed!

South Hills Without the Snow

03/05/2021

Under all that snow was the foundation for the addition’s grade beams.

Snow at South Hills!

02/19/2021

This had to be documented… Take a look at all the snow at South Hills!

Prepping for Parking!

01/04/2021

The concrete has been placed for the front drive and the south parking lot is being prepped for its own […]

Foundation is Key

12/29/2020

The foundation pier installation is ongoing and progressing nicely!

The New Building is Connected

12/11/2020

The steel has been set and Building H is now a part of South Hills High School

Main Entry + Building H

11/13/2020

The concrete crew is working on finishing the concrete pour at the new entry and at Building H.

Back on Track

09/04/2020

Paving demolition is complete, and the utility work has begun

Mobilizing

07/10/2020

We demoed and hauled off the portable for the project. Just look at those views!

Initial Demo

06/26/2020

Demolition is still underway, and we’re taking care of all of the little things like re-routing fiber and copper cables!

Make Way for the New Addition!

06/18/2020

We’re demoing the portable classroom to make way for the new addition

The Demo Days Begin

06/12/2020

First on the demolition list: the pavement!

Adios Asbestos!

05/29/2020

Asbestos abatement is underway in 3 portables, and we plan to mobilize early next week. Let the construction begin!

Bid Opportunity & Pre-Proposal Meeting

05/08/2019

Pre-proposal meeting to be held on Wednesday, May 15, 2019 at 10:00 AM for the bid opportunity RFQ – CMAR […]

Conceptual renderings of SHHS New Building Addition

05/07/2019

Preliminary architectural renderings provide a glimpse of the new classroom building addition at SHHS.

Students Drawing and Discussing

11/19/2018

The architects, Jacobs & Associates, held a student design charrette at South Hills High School. Students were given a layout […]