North Side High School will receive improvements and an addition to the existing Mariachi Hall.
KEY INFORMATION
Trustee
Dr. Camille Rodriguez
Budget
$3,151,382
Opening Date
October 2020
Design Process
Address
2211 McKinley Ave
Fort Worth, TX 76164
4,969
New Square Footage
N/A
Renovated Square Footage
Construction Process
PROJECT TEAM
Sample avatar
Edsel Gaitonde
Edsel Gaitonde
Owner Representative
Pinnacle Contracting Group
Contractor
WRA Architects
Architect

EMAIL UPDATES

Subscribe below to receive North Side High School email updates.
PROJECT UPDATES
Rediscover FWISD

06/29/2021

Northside’s additions include a 4,969-square-foot Mariachi Hall that is home to the School’s award winning Mariachi Program

Project Complete!

11/18/2020

The Northside Mariachi project is officially complete!

Mariachi Hall

10/16/2020

The new Mariachi Hall Addition is complete!

Finishing Touches

09/18/2020

The mural is complete and interior cleanup is ongoing.

Mural Update

08/21/2020

The exterior mural is nearly complete!

Exterior & Interior Updates

08/07/2020

The mural is making great progress, meanwhile, the flooring has been installed and the millwork has arrived.

Mural Progress

07/31/2020

The exterior mural at the new mariachi addition continues and will bring a new energy and focus to the east […]

Mural Background

07/24/2020

The mural background has started!

Painting in Progress

07/17/2020

Painting has begun! Look at all those beautiful colors!

Ready for the Mural

07/10/2020

The drywall install is complete, and the mural artists has begun priming. We can’t wait to see the finished product!

Exterior Update

06/26/2020

With stucco work complete, the capstone installation along the paraphet wall has begun!

Windows + Walls

06/12/2020

We have completed the window wall framing and are still working on the interior drywall and the exterior brick

Wall Work

05/29/2020

The exterior brick work and the interior drywall installations are both ongoing, and the exterior stucco will be beginning shortly!

Almost Framed to Perfection

05/15/2020

Framing is up in all areas but the restroom, meanwhile, the exterior brick work is progressing!

Raise the Roof.. Top Units

04/20/2020

The roof top units were set on this past Thursday.  Work on the HVAC ductwork is continuing.  Weather permitting, the […]

Wall to Wall Excitement

04/03/2020

The exterior walls, structural steel, and metal deck are all completed and installed. Fingers crossed for warm weather to help […]

Progress Report!

02/27/2020

CMU walls are going vertical — we’re moving along swiftly here at North Side High School.

Blocks on Blocks on Blocks

02/25/2020

The building is taking shape! The CMU on the southwest corner adjacent to buildings B & C is almost topped […]

Strong, Reliable, and Versatile.

02/13/2020

Did you know: CMU is one of the most versatile building products?! We want only the best for this project – […]

Concrete Delivery Service

02/05/2020

We’ve received our first delivery of CMU blocks which will be used to form the walls of the new Mariachi […]

The Concrete is Coming!

01/29/2020

With all the rain that we’ve been getting, we’ve had to push back the concrete pour. However, the rebar was […]

Grade Beams in Progress

11/07/2019

Foundation grade beams are being excavated and formed!

Piers!

10/15/2019

Piers were drilled, installed and poured.

Moving Dirt

09/25/2019

Earthwork and foundation work has begun!

Gas Line Relocation

08/08/2019

Relocation of existing gas line.

Sneak peek!

11/13/2018

Here is a sneak peek of a rendering of the new Mariachi addition that WRA Architects will be including in […]

Pre-Proposal Meeting Recap

11/10/2018

A pre-proposal meeting was held where vendors could find out more information about aspects of the procurement process, proposal requirements, […]

BID OPPORTUNITY: PRE-PROPOSAL MEETING

10/30/2018

A pre-proposal meeting will be held on Thursday, November 8th, at 4:00pm for the bid opportunity, CSP – BP 19-030 […]