Eastern Hills High School will receive new Science classrooms and labs.
Common spaces will be renovated to create collaboration spaces for learning and student interaction. Moderate renovations will be applied to various locations within the school to meet the twenty-first century learning model. Renovations will include reclaiming or repurposing space to support Career and Technical Education.
KEY INFORMATION
Trustee
Tobi Jackson
Budget
$48,385,451
Opening Date
November 2021
Design Process
Address
5701 Shelton St
Fort Worth, TX 76112
55,303
New Square Footage
149,779
Renovated Square Footage
Construction Process
PROJECT TEAM
Sample avatar
Stoney Crump
Stoney Crump
Owner Representative
Cadence McShane
Contractor
VLK Architects
Architect

EMAIL UPDATES

Subscribe below to receive Eastern Hills High School email updates.
PROJECT UPDATES
Substantial Completion Has Been Reached!

12/01/2022

What a Beauty!

Primed and Painted!

01/07/2022

The baseball outfield wall has been primed and painted

Cafeteria Patio Complete!

12/15/2021

The cafeteria’s patio is officially complete!

Cafeteria Furniture

12/10/2021

The new furniture has been brought into the cafeteria!

Latest Canopy Updates

11/12/2021

The cafeteria canopy is wrapping up!

All in the Details

11/03/2021

Take a look at the details in the cafeteria canopy!

Cafeteria Canopy Progress!

10/29/2021

The cafeteria canopy continues to make great progress!

Cafeteria Canopy Coming Along!

10/15/2021

The new Avodek canopy at the cafeteria patio installation is moving right along!

Graphic Updates

10/13/2021

More graphics are wrapping up inside of Eastern Hills!

Pride of the Eastside

10/01/2021

The athletics building graphics and scoreboard got a facelift! Take a look at the new graphics

Interior Graphics

10/01/2021

A few graphics are wrapping up inside Eastern Hills!

Front Entrance & Landscaping

08/13/2021

The main entrance is complete and the new landscaping has been installed along Weiler Blvd.

Auditorium Complete!

08/11/2021

The auditorium is prepped for registration and welcoming teachers back!

Cafeteria Progress

08/06/2021

The renovations in the Cafeteria are going well and nearly complete!

Furniture & Fixtures!

08/04/2021

FF&E have been delivered to the Administration Conference Room, Assistant Principal office and a collaboration space

More Finishes!

07/28/2021

The Media Center’s wall tiles and countertops have been installed!

Media Center + New Entry Graphic!

07/23/2021

All the furniture for the media center has been delivered and set up!

Cafeteria& Band Hall Progress

07/20/2021

The Band Hall walls and open sections of the ceiling have been painted. Ceiling grid and acoustical panel installation is […]

Scoreboard & Graphics Complete!

07/15/2021

The graphics and the scoreboard installation is complete! GO HIGHLANDERS!

Classroom Renovation

07/09/2021

Take a peek at some of the latest classroom renovations! These photos show the LINC & SPED classrooms

Band Hall Renovations

07/07/2021

The corridor and percussion/ensemble/storage rooms have plumbing installed and wall framing is in-progress, and the band hall walls and open […]

New Main Entrance

07/01/2021

The new entrance is receiving a few final touch-ups and the new school logo will be installed soon!

Upper Level Corridor

06/25/2021

The upper level corridor stairs are complete, and the wall has been prepped for the Eastern Hills graphic!

Onto Phase 4

06/18/2021

The Band Hall walls and open sections of the ceiling have been painted. Ceiling grid installation is in-progress, renovations in […]

Completion Happening All Over Campus

06/11/2021

The upper level men’s restroom, corridor, and collaboration spaces are complete!

Stencil Started!

05/26/2021

The graphic stencil has been started for the athletics facility

Sun Shades Installed

05/14/2021

The sun shades on the east elevation have been installed!

More Interior Finishes!

04/30/2021

The media center collaboration rooms, upper and lower mezzanines, and the main-level administration are all complete!

Weight Room = Complete!

04/23/2021

The weight room in the fitness center is complete! New epoxy floors have been installed, and soon all of the […]

Main Entrance Complete!

04/02/2021

Take a look at the new exterior of the main entrance and the completed terrazzo flooring!

New, New, New

03/12/2021

New terrazzo flooring with school letters are currently being installed at the Main Entrance. New classroom furniture has been installed […]

Media Center Updates!

03/05/2021

The ceiling, light fixtures, and wall paneling install is moving along swiftly!

Entrance & Interior Update!

02/19/2021

The stone installation for the addition’s main entrance is ongoing. Meanwhile, take a look at the nearly complete corridor!

Exterior Improvements are Happening All Over This Site!

01/22/2021

While installation of the windows & paneling on the new addition continues, the main entrance to campus is officially open!

A Few Finishes!

01/04/2021

Look at some of the completed renovations!

Interior & Exterior Update

12/29/2020

The Upper-Level Area D phase 2 is complete and the installation of the wall paneling on the new addition is […]

RENOVATION COMPLETE!

12/11/2020

Renovation work in the Cyber Security Room are officially complete!

EHHS Modernization Well Underway!

11/13/2020

Brick installation has begun on the east and west elevations of the new building addition. In addition, interior renovations will […]

Ready for the Exterior Finishes!

10/23/2020

Stone veneer and brick have been delivered and soon to be installed on the new addition

Roofing & Framing

10/16/2020

The roof installation is 80% complete. The new building addition’s walls have been insulated and almost ready for the brick […]

Moving In!

10/02/2020

Several of the classrooms are complete and ready for social-distanced learning!

Addition Progress

09/04/2020

The top floor of the addition’s wall insulations and roof panels are being installed

Athletics Project Finishing Touches

08/28/2020

The athletics project is coming to an end. The lockers have been installed, the locker rooms are complete, and the […]

Furniture Progress

08/26/2020

The Phase 1 classrooms are ready to be furnished!

Furniture Ready

08/21/2020

The millwork for the administration offices is complete and ready for more furniture to be brought in. Meanwhile, the pier […]

Nearly Complete

08/07/2020

The Athletics project is close to finishing. The cabinetry has been installed in the assistant coaches office and the training […]

Finished Areas

08/05/2020

Corridors and Classrooms with flooring, ceiling, and wall tiles installations are complete, and all finished are being cleaned.

A Few Finalizations

07/24/2020

The main level in Unit C is tiled, and classrooms are nearly complete.

Tiling is Nearly Complete

07/15/2020

The restroom tiling is nearing completion, and the main level corridor tile install is ongoing

Fitness Center Installs

07/13/2020

The storage room doors are being installed in the Fitness Center, and exterior wall paneling continues

Ceilings and CMU

07/10/2020

The ceiling installations are complete, the roof is being installed for the addition, and the CMU walls in the locker […]

Up with the Steel!

07/08/2020

Things are progressing nicely here at Eastern Hills. The steel installation for the main campus addition is ongoing.

In Addition…

07/03/2020

The steel erection for the addition has been installed, and the corridor wall tiles and ceiling grid installation is ongoing.

Powering Through the Panels

07/01/2020

The work for the exterior wall paneling systems is ongoing.

Installations, Painting, and More!

06/26/2020

The fitness center’s ceiling insulation installation and paint work is ongoing. At the Athletics Addition, walls are complete and ready […]

Tiling and Wall Framing Continues

06/24/2020

Floor and wall tile in the SPED Classroom’s restroom is complete. Meanwhile, wall framing in the new administration area is […]

Athletics Progress

06/15/2020

The exterior ramp and stairs to the field have been completed, and the perimeter and interior walls have reached full […]

Demolition Continues

06/12/2020

Demolition is underway at the administration and counselor areas.

Masonry Work

06/05/2020

The masonry work is going steady! We’re continuing the work on the addition’s perimeter walls, door and window frames, and […]

All About Abatement

06/01/2020

The abatement in the administration offices and the main level is complete!

More Walls!

05/29/2020

The masonry work is progressing as the addition perimeter walls begin to take shape. Next are the door and window […]

So, it Continues…

05/20/2020

Although demolition of the main administration offices is complete, abatement has just begun! The admin offices are being prepped for […]

We’re Going to Have Walls!

05/15/2020

The contractor has started the installation of the perimeter walls, door frames, and window frames

Abatement + Demo

05/13/2020

The contractor has started to demo the administration offices, meanwhile, abatement continues in the main level and will progress towards […]

What Else is New?

05/08/2020

Check out the new concrete slab for the addition at the north end! On the inside, we have the tiles […]

Focusing on Concrete

05/06/2020

Prep work for concrete pours are happing all over our jobsite! We’re prepping the new driveway for the final concrete […]

Storage Room Status

05/01/2020

All the flooring has been removed and the new storage rooms have been constructed in the renovation. Installation of the storage […]

Slabs Poured & Dates Decided

04/29/2020

The Area E slab has been poured, and we have scheduled our completion dates. We are so excited for the […]

Out with the Old, In with the New!

04/15/2020

The main entrance has been demoed, and the renovation materials are ready for installation

Sweep the Perimeter!

04/13/2020

The construction for the perimeter foundation is coming along nicely, the soil compaction for the addition is progressing, and the […]

Rain Delays

03/20/2020

Unfortunately, due to rain delays, the drilling schedule for both additions to the high school and athletics has been pushed […]

Sayonara, Canopy!

02/27/2020

We demoed the existing canopy and are now prepping for the new addition.

No Soggy Softball Fields!

02/25/2020

The installation for the softball field’s new storm water drain is progressing and all the weight room equipment has been […]

Farewell, Rooms 102, 103, & 105!

02/25/2020

All of these rooms have been demoed and the millwork has been disposed of. A new corridor door has been […]

Bring On The Installations

02/19/2020

Installations are happening all throughout this project! The new utilities for the addition are being installed, and the new drainage […]

Site Grading: A+

02/05/2020

The site grading for the addition continues along the northwest corner of our jobsite, while the installation of the wastewater […]

You Gotta Start Somewhere!

01/22/2020

The new northwest parking lot and building addition has been graded (photo 1) and on the interiors, we have begun […]

Bring Out the Excavators!

01/13/2020

We have broken ground for the athletics portion of the project! We are currently demoing the concrete walkway as well […]

The First Look at Construction

01/10/2020

From design to real life! We are so excited to have the Eastern Hills Addition and Renovation project underway. The […]

Rendering a Larger Look

04/10/2019

Conceptual renderings give an idea of what some of the renovations and addition may look like in the school, including: […]

A New Library for Bright Minds

04/02/2019

Students are sure to embrace the proposed new media center with student collaboration spaces, book stacks, a new tech help […]

Conceptual Renderings Give Glimpse of Proposed Renovations

03/29/2019

Conceptual renderings highlight proposed front entrance to Eastern Hills HS and new building addition

Reviewing preliminary designs

03/06/2019

VLK Architects showing preliminary designs of the renovation and addition to Eastern Hills High School.

Pre-Proposal Meeting Recap

02/20/2019

A pre-proposal meeting was held for the bid opportunity, RFQ-CMAR 19-102 Eastern Hills HS Addition/Renovation, where vendors found out more […]

Bid Opportunity & Pre-Proposal Meeting

02/13/2019

A pre-proposal meeting will be held on Wednesday, February 20, 2019 at 10:00 am for the bid opportunity RFQ – CMAR 19-102 Eastern Hills […]

Students designing their own space

10/05/2018

VLK Architects recently held a student design charrette at Eastern Hills High School to seek student input and ideas for […]