Dunbar High School will receive an expansion to the existing field house.
KEY INFORMATION
Trustee
Quinton "Q" Phillips
Budget
$3,949,754
Opening Date
January 2020
Design Process
Address
5700 Ramey
Fort Worth, TX 76112
4,000
New Square Footage
9,000
Renovated Square Footage
Construction Process
PROJECT TEAM
Sample avatar
Mark Goessler
Mark Goessler
Owner Representative
Construction Zone
Contractor
IDG Architects
Architect

EMAIL UPDATES

Subscribe below to receive Dunbar High School email updates.
PROJECT UPDATES
A Few More Finishes

01/13/2020

Dunbar Athletics is complete!

Coaches' Office Complete

01/13/2020

Weight Room & Locker Room

01/13/2020

The weight room and the locker room are complete!

What Team? Wildcats!

12/23/2019

We’re almost set to welcome all the Wildcats! Take a look at some of the completed aspects for the new […]

Finishing Touches

11/20/2019

The women’s locker room is ready to welcome the girls & their coaches (photo 1). The men’s restroom is completely […]

Construction Progressing

11/07/2019

Weight Room (Photo 1) has lighting and overhead work completed and awaiting flooring. Restroom Showers (Photo 2) have been tiled. […]

Working on the Outside and the Inside

08/29/2019

The brick veneer is being installed on the addition. The girl’s locker room is constructed and the roof is complete.  […]

Working Hard Inside and Out

08/16/2019

Moisture protection is being applied to exterior of the addition, along with steel support beams, roof joist and CMU walls […]

Masonry Walls are going up!

08/01/2019

New structural beams are being installed, temporary shoring removed and structural flooring installed. The final support beams for connection of […]

Concrete!

07/08/2019

New reinforced concrete slab with vapor barrier has been installed at new addition to the Dunbar Athletic Facility.

Construction is quickly moving along

06/17/2019

Interior demolition of the existing field house is complete and installation of new electrical work is in underway. The contractor […]

Interior Demolition Days

03/21/2019

Interior demolition is well underway of the existing Dunbar Field House in preparation for the building renovation and addition.

Pre-Proposal Meeting Recap

12/04/2018

A pre-proposal meeting was held where vendors could find out more information about aspects of the procurement process, proposal requirements, […]

Bid Opportunity and Pre-Proposal Meeting

11/26/2018

A pre-proposal meeting will be held on Tuesday, December 4th, at 9:00am for the bid opportunity, CSP-BP 19-042 Dunbar HS […]

A New Expansion

11/13/2018

A sneak peek of a computer rendering of the expansion to the existing field house.