Benbrook MS/HS will receive a new baseball & softball complex.
KEY INFORMATION
Trustee
Dr. Michael Ryan
Budget
$7,188,679
Opening Date
January 2020
Design Process
Address
201 Overcrest Dr.
Fort Worth, TX 76126
4,060
New Square Footage
N/A
Renovated Square Footage
Construction Process
PROJECT TEAM
Sample avatar
Drew Schott
Drew Schott
Owner Representative
Muckleroy & Falls
Contractor
Hahnfeld Hoffer Stanford
Architect

EMAIL UPDATES

Subscribe below to receive Benbrook Middle-High School email updates.
PROJECT UPDATES
Fields Complete!

The Benbrook Softball and Baseball fields are ready for season!

Season Opener

02/24/2020

Time to celebrate! The fields and concession building are open to the district and public! The baseball teams have already […]

Let’s Talk Turf

02/14/2020

Landscaping is happening all over the ballfields, but we’re happy to announce that the turf is finally installed at the […]

Top of the 9th

01/29/2020

We’ve past the seventh inning stretch, we’ve rounded third base, and we’re headed home! The Benbrook ballfields are nearly finished. […]

Take Me Out to Benbrook

01/21/2020

We’re rounding third base with this project! Take a look at the fields and stands all the Benbrook students and […]

No Stalling Allowed on Installations!

01/14/2020

Installations are happening here, there, & everywhere! We have the bleachers being installed (photo 1), the roofing being installed on […]

Construction Eye View + Birds' Eye View

12/11/2019

Baseball and Softball players don’t want a bumpy outfield, and we don’t want bumpy sidewalks! We’re smoothing out the concrete […]

Concession Building and Field Work Progressing

11/07/2019

The exterior concrete masonry block (CMU) of the Concession Building is near complete. Fencing is being installed and the ballfield’s […]

Concession Building is being Built

10/12/2019

The concession building slab has been poured, and its masonry work and setting of door frames is underway. The irrigation […]

Concrete Pour

09/25/2019

Fire Lane and parking lot concrete has been poured, now working on fencing post and block walls.

Lime, Walls, Plumbing and Electrical

08/29/2019

Lime treatment has started at the new parking lot.  Work is continuing on the retaining walls, and the backstop concrete […]

Installation!

08/14/2019

New retaining walls are being installed along with underground electrical work and the underground rough-in for plumbing.

Concrete, preparation and excavation

07/30/2019

Concrete footing has been installed for backstop and excavation is underway for the retaining walls.  A brick mock up for […]

Preparing for retaining walls!

07/16/2019

Forming grade beams for retaining walls at the baseball field before pouring concrete.

A Brighter View

07/08/2019

New Baseball and Softball field lighting installation.

A Preliminary Rendering

05/06/2019

A preliminary rendering gives a glimpse of how the new fields may look.

Demo!

04/08/2019

Demolition and excavation of existing ballfield.

Pre-Proposal Meeting Recap

01/22/2019

A pre-proposal meeting was held where vendors could find out more information about aspects of the procurement process, proposal requirements, […]

Bid Opportunity & Pre-Proposal Meeting

12/19/2018

A pre-proposal meeting will be held on Tuesday, January 8th, at 2:00pm for the bid opportunity, CSP – BP 19-032 […]

Designing a new Baseball-Softball Complex

10/12/2018

Design is well underway for a proposed baseball-softball field complex to serve the students of Benbrook MS/HS. The complex will […]