Benbrook MS will receive a new competition gymnasium with bleacher seating and dressing areas. The HS will receive a new Fine Arts addition for the Band Hall, Orchestra, Choir, STEM classrooms and collaboration space. There will also be additional parking provided on this campus.
KEY INFORMATION
Trustee
Dr. Michael Ryan
Budget
$19,553,255
Opening Date
August 2020
Design Process
Address
201 Overcrest Dr.
Fort Worth, TX 76126
37,679
New Square Footage
7,784
Renovated Square Footage
Construction Process
PROJECT TEAM
Sample avatar
Drew Schott
Drew Schott
Owner Representative
Adolfson & Peterson Construction
Contractor
LBL Architects
Architect

EMAIL UPDATES

Subscribe below to receive Benbrook Middle-High School email updates.
PROJECT UPDATES
Latest Aerials

12/20/2021

Take a look at the newest aerial shots of Benbrook!

All in the Details

08/13/2021

The new addition and gymnasium is covered in Bobcats!

New Locker Rooms

08/06/2021

Take a look at the new locker rooms!

Bobcat Pride!

05/26/2021

Take a look at the signage in the new middle school gym!

Brickwork Touch-Ups!

04/08/2021

The high school addition’s brickwork is nearly complete!

Latest Aerials

03/12/2021

You’ve seen all the brickwork that’s been happening from ground-level… but how about a bird eye’s view?

From the Ground Up!

03/05/2021

The brickwork continues here at Benbrook and is moving along swiftly!

Brickwork at Benbrook!

02/19/2021

The brickwork is ongoing for Benbrook Middle School!

Raise the Roof!

12/11/2020

The high school addition is furthest along with the roof already installed and the brick work nearly done. The middle school […]

Addition is Underway!

12/02/2020

The CMU installation for the new middle school addition is 80% done! Up next is the storm shelter.

CMU Update

11/13/2020

Take a look at the latest CMU wall update! The project is moving right along!

CMU Walls are Going Vertical!

10/23/2020

The CMU installation for the new middle school gymnasium and fine arts area is making progress!

High School Foundation

08/21/2020

Landscape Beautification

08/14/2020

The middle school’s exterior landscape is nearly complete

New Building Additions are Shaping Up

07/31/2020

Progress is being made for both the high school and middle school additions. The rebar installation for the middle school […]

Still Drilling

07/15/2020

The pier drillers are out drilling for the Middle School addition. Up next will be grade beams and pouring a […]

Ongoing Exterior Work

07/10/2020

There is a fair amount of exterior work to still be taken care of, but we are working hard to […]

Exterior Work

06/12/2020

The demolition of the interiors for both the high school and middle school are nearly complete. Our main focus will […]

Beginning Demolition

05/29/2020

As we wrap up the parking lot project, we are beginning to demo both the high school and middle school […]

Final Pours and More

05/22/2020

The last parking lot is nearly complete! The concrete was poured last week, and we will begin striping it once […]

Final Parking Lot Pour

05/15/2020

The third and final parking lot has been poured and the parking lot project is nearly complete!

Demolition Derby?

05/08/2020

Our site may look like the track for a demolition derby – but the only demolition happening here is the […]

Taking it Inside!

05/01/2020

While the work that has been going on has consisted mostly of exterior work, we are now gearing up to […]

A Surplus of Sewer Updates

04/24/2020

We are working on the sanitary sewer! We have been excavating the areas and are going to begin installation soon.

Move the Dirt, Bring on the Concrete!

03/06/2020

We’re working on removing all the excess dirt in order to make room for the fill. Up next, we are […]

When It Doesn’t Rain, We Pour!

02/27/2020

We’ve poured concrete for the high school parking lot which is now being striped for parking stalls.

Parking Lot Party

01/29/2020

The parking lot addition continues! Throughout these next few weeks we’ll be having concrete pours to start making this parking […]

Bring on the Rain! (After the Project, Of Course)

01/22/2020

An even larger storm line was installed! Benbrook will be prepared for all the rain with this storm line.

Prepare for Parking!

01/17/2020

Parking lot progress report! We are still working hard on the parking lots to wrap up the commotion quickly. Bountiful […]

From Dirt Lot to Parking Lot

01/14/2020

The rough grade of the first portion of the parking lot is complete! Work is progressing nicely and we look forward […]

Pre-Proposal Meeting Recap

03/21/2019

A pre-proposal meeting was held for the bid opportunity, RFQ-CMAR 19-099 Benbrook MS/HS Addition/Renovation, where vendors found out more information […]

Bid Opportunity & Pre-Proposal Meeting

03/05/2019

Pre-proposal meeting to be held on Wednesday, March 20, 2019 at 2:00 PM for the bid opportunity RFQ – CMAR […]

Student Ideas for the Future

11/19/2018

LBL Architects recently held a student design charrette at Benbrook Middle-High School. Students designed their vision of various new spaces […]