Arlington Heights High School will receive a new Athletic Facility.
KEY INFORMATION
Trustee
Kevin Lynch
Budget
$3,617,512
Opening Date
September 2020
Design Process
Address
4501 W Freeway
Fort Worth, TX 76107
6,040
New Square Footage
4,820
Renovated Square Footage
Construction Process
PROJECT TEAM
Sample avatar
Cale Wilkinson
Cale Wilkinson
Owner Representative
Philips | May – Basecom
Contractor
Hahnfeld Hoffer Stanford
Architect

EMAIL UPDATES

Subscribe below to receive Arlington Heights High School email updates.
PROJECT UPDATES
Arlington Heights Athletics = Complete!

Nearly Finished

08/07/2020

The general contractor is continuing to work on the punch list

Laying Down the Sod!

07/10/2020

The new sod is being installed! This project is coming to an end!

New Athletics Building Sneak Peek

06/26/2020

Check out the new boys athletic locker room and coaches’ office!

Working Toward Final Touches

06/12/2020

Check out the finished sidewalks, coaches’ office, as well as the finished grading! The finish line is getting closer!

What About the Existing Field House?

05/29/2020

We’re been talking a lot about the new athletics building, but we haven’t forgotten the beloved field house! To catch […]

Framing the Field House

05/22/2020

The wall framing is going up in the new trainers’ room as well the restrooms!

The “To Be Continued…” List

05/15/2020

Our completion list continues to grow; however, we still have plenty on our checklists. Our primary focuses are sealing the […]

What's New!?

05/01/2020

We’re still cruising at Arlington Heights! The water to the building has been connected, work on the exterior backfill of […]

What We’re Working On

04/20/2020

The exterior backfill of the foundation is progressing, the electrical secondary conduit has been installed, and we’ll be working on […]

Almost Abatement Ready

04/03/2020

While the exterior backfill of the foundation continues, we are awaiting the abatement work in the existing field house to […]

Crushing Our Checklists

03/20/2020

We’re plowing through our to-do’s like there’s no tomorrow! We’ve gotten a lot accomplished recently, and we can’t wait to […]

Let’s See That Scaffold!

02/27/2020

We’re working on the scaffold in preparation for the brick work

Raise the… Ceiling!

02/24/2020

The drywall has been installed in the restrooms and the plaster has been installed in the showers. The interior work […]

Insider's Sneak Peak

02/19/2020

The masonry work has been the star of the show for quite some time now, what about our interiors!? The […]

Teamwork Makes the Dream Work!

01/29/2020

We are working this project in any way possible! We have the exterior face brick beginning, the interior painting continuing, […]

All About That Base

01/22/2020

The base courses of face brick is being laid for the West Elevation (photos 1 & 2) and we have […]

Onto the Interiors!

01/14/2020

With the exterior concrete masonry unit being complete, we are now working hard on the interiors. The plumbing, electrical, & […]

Concrete Evidence of Project Progression!

12/23/2019

The exterior concrete masonry unity walls are nearly complete and the interior CMU walls are making great strides. Up next: […]

What Makes a Wall

11/20/2019

Structure and foundation are KEY! The slab-on-carton void is complete (photo 1), the walls of the athletic building are going […]

Foundation Slab at Athletic Building Addition Progressing

11/07/2019

Pouring the final concrete for the slab

Plumbing Underway

10/12/2019

Under slab plumbing is being completed in preparation of slab pour.

Forming and Pouring

09/25/2019

Forming beams and pouring beams for the future addition.

Forms

08/29/2019

Progress is being made in forming and preparing the grade beams for the Athletic facility.

Drilling and Pouring

07/30/2019

Drilling and pouring concrete for foundation piers.

Securing the job site

04/08/2019

Workers define and secure the job site with temporary fencing.

Pre-Proposal Meeting Recap

01/22/2019

A pre-proposal meeting was held where vendors could find out more information about aspects of the procurement process, proposal requirements, […]

Bid Opportunity & Pre-Proposal Meeting

12/19/2018

A pre-proposal meeting will be held on Wednesday, January 9th, at 9:30am for the bid opportunity, CSP – BP 19-031 […]

Sneak Peek!

11/13/2018

A sneak peek of a rendering of the new Arlington Heights Athletics Facility.