Arlington Heights High School will receive a new multi-story classroom building.
Common spaces will be renovated to create collaboration spaces for learning and student interaction. Moderate renovations will be applied to various locations within the school to meet the twenty-first century learning model. Renovations will include reclaiming or repurposing space to support Career and Technical Education.
KEY INFORMATION
Trustee
Anne Darr
Budget
$51,199,403
Opening Date
January 2022
Design Process
Address
4501 W Freeway
Fort Worth, TX 76107
51,730
New Square Footage
93,335
Renovated Square Footage
Construction Process
PROJECT TIMELINE
In Design Nov 1, 2019 - Nov 17, 2019
Under Construction Nov 15, 2019 - Nov 23, 2019
Move In Nov 13, 2019 - Nov 15, 2019
Open Nov 20, 2019 - Nov 24, 2019
Post Construction Nov 7, 2019 - Nov 30, 2019
PROJECT TEAM
Sample avatar
Harold Leeman
Harold Leeman
Owner Representative
Satterfield & Pontikes
Contractor
Hahnfeld Hoffer Stanford
Architect

EMAIL UPDATES

Subscribe below to receive Arlington Heights High School email updates.
PROJECT UPDATES
Beaming!

07/15/2020

Work for the grade beams for the Ag Building and for the new Science Building is ongoing

Exterior Update

07/10/2020

The Science Building beams are up!

Prepare the Dance Floor

07/03/2020

The floor in the dance studio is being prepped, electrical work in classrooms is ongoing, and the grade beam work […]

Out With the Old, In With the New

06/26/2020

The old roof over the jewelry lab was torn off, and we have begun installing the new roof!

Talk About Demolition

06/12/2020

We’ve had a busy week! The demolition is complete at the new security entrance, we’ve been demoing the Jewelry lab […]

Keeping Busy!

05/29/2020

SFP2 completed the majority of the new sanitary sewer pipe in the courtyard, interior abatement and demolition of the ground […]

Progress Report!

05/01/2020

The movers started in the jewelry lab removing all the equipment, supplies and furniture as well as other rooms in the […]

“Early” Is Our Favorite Word!

04/20/2020

Our construction team has been making incredible progress these past two weeks. Piers for the foundation for Building D have […]

Sewers For the Science Building

03/20/2020

The sanitary sewer line has been installed by the new science building!

Bring on the Transformer

We are working hard to finish prepping the concrete pad for the electrical transformer and the connection enclosure.

Site Prep!

02/14/2020

Site preparation is underway for the Arlington Heights Science Building, and the electrical service conduits are being installed for the […]

So Long, Portable Buildings!

01/22/2020

Demolition has officially begun! We demoed the portable buildings, began working on the formwork for the transformer pad, and are […]

Pre-proposal Meeting Recap

05/07/2019

A pre-proposal meeting was held for the bid opportunity, RFQ-CMAR 19-101 Arlington Heights High School Addition/Renovation, where vendors found out […]

Exploring for a New Foundation

03/15/2019

Soil sampling to understand the makeup of the ground under the foundation of the future science addition.

Students’ Ideas for Design

11/13/2018

Architects, Hahnfeld Hoffer Stanford, recently held a student design charrette at Arlington Heights High School. Thought-starter image boards featuring exterior […]