O.D. Wyatt High School’s common spaces will be renovated to create collaboration spaces for learning and student interaction. Moderate renovations will be applied to various locations within the school to meet the twenty-first century learning model. Renovations will include reclaiming or repurposing space to support Career and Technical Education.
KEY INFORMATION
Trustee
Wallace Bridges
Budget
$43,668,821
Opening Date
March 2022
Design Process
Address
2400 E Seminary
Fort Worth, TX 76119
25,600
New Square Footage
175,961
Renovated Square Footage
Construction Process
PROJECT TEAM
Sample avatar
Mark Goessler
Mark Goessler
Owner Representative
Satterfield & Pontikes Construction - Post L Group
Contractor
Harrison Kornberg
Architect

EMAIL UPDATES

Subscribe below to receive O.D. Wyatt High School email updates.
PROJECT UPDATES
Substantial Completion Has Been Reached!

12/07/2022

Check Out This Before & After Transformation!

Corridors Complete!

04/29/2022

The graphics in the art corridor have been installed!

Science Signage!

04/15/2022

Take a look at the new hallway signage for Area J!

New Casework!

04/15/2022

The casework in the new science lab has been installed!

Corridor Renovation

03/28/2022

The renovations for Area J’s corridors are moving right along!

Area J Build Back Complete!

03/18/2022

The build back in Area J is complete! The furniture installation is next on deck.

Panels & Tile Installs

03/04/2022

Ceramic tiles are being installed in the restrooms, meanwhile, PSI panels are being installed in the corridors

Science Lab Update

02/24/2022

Things are moving right along in the science lab renovation with MEP rough in and a new wall going in […]

New Ceilings & Classroom

02/18/2022

The ceiling grid is being installed in Area J. Take a look at the bones of the new classrooms!

Corridor & Ductwork

02/04/2022

The build-back of area J continues with the installation of metal stud walls, electrical rough in, and ductwork.

Area J Progress

01/21/2022

The demolition is complete in Area J and the build-back is making great progress!

Parking Lot Progress

01/14/2022

The grading of the new west parking lot is moving right along!

Area J

01/07/2022

New ductwork and wall-framing is going into Area J!

A Few Finishes

12/10/2021

Take a look at the new reception desk graphics and the finished media center corridor

Completed Front Entry!

11/03/2021

The exterior addition at O.D. Wyatt High School and the new front entry are complete! Interior construction is ongoing and […]

OD Wyatt Graphics

10/29/2021

Take a look at some of the new internal graphics that have gone up around OD Wyatt!

Area H Build Back

10/01/2021

The build back of Area H continues!The drywall installation and MEP rough in are making great progress

Cafeteria Coming Together!

08/20/2021

The cafeteria is making great progress!

Significant Project Progress

08/18/2021

The O.D. Wyatt CTE building and front entry project has made significant progress over the past few months. Inside the […]

CTE Building

07/09/2021

Inside the CTE Building! Take a look at some of the finishes and a completed classroom!

New Entry + CTE Building!

06/25/2021

Take a look at the progress being made on the new entryway and the CTE building

Awaiting Furniture

06/18/2021

The new media center is complete and ready for furniture to be brought in!

Classroom Update

05/26/2021

A few of the classrooms in Area F are complete and the CTE classrooms are underway!

Ready for the Choir!

04/30/2021

Take a look at the new choir room!

Exterior Updates

04/16/2021

The Front Entry has been secured, and the aluminum storefront has been installed.

Taking Shape!

03/05/2021

The addition’s front entry is taking shape and the North CTE Building is coming along nicely!

CTE Exterior Brickwork Complete!

02/05/2021

The exterior brick installation for the new CTE building is complete! Metal Panels will soon be installed to complete the […]

Light and Bright!

01/22/2021

The auditorium received a new acoustical ceiling with LED lighting.

CTE & Front Entry Progress

01/04/2021

The CTE Building & the front entry are making great headway!

New CTE Building Construction Progress

12/11/2020

The exterior metal stud walls and sheathing on the CTE building is complete!

The CTE Building is on the MOVE!

12/02/2020

Remember when the CTE Building was just a concrete slab? Look at it now! Wall framing and exterior sheathing is […]

New Point of View

11/13/2020

The exterior walls and mechanical work for the new CTE building continues.

CTE Update

10/16/2020

Take a look at the framework for the new CTE building!

CTE Building

09/04/2020

The structural steel setting for the CTE building continues

Admin Area

08/28/2020

The furniture for the administration was brought in!

New Career Technical Education Building

08/14/2020

The foundation slab has been poured. Next up, steel structure work will begin!

Exterior Update

08/07/2020

The work on the sidewalk and bus lane canopy continues, and the scaffolding for the auditorium has started.

Exterior Work

07/24/2020

The new CTE building work continues, and the concrete has been placed for the new bus lane

Ductwork

07/17/2020

The ductwork is ready for installation in Area A, while the ductwork in the corridor between the Auditorium and the […]

Onto Metal Studs

07/15/2020

Ductwork and metal stud installation is ongoing in the Administration area, meanwhile, metal stud framing is going up in the […]

Beginning to Frame

07/10/2020

Metal stud framing for the administration area and the north east section of the renovation is being installed

Safety First

07/03/2020

We’re setting up the main water line trench for fire protection as well as metal stud framing in the new […]

Getting to Work!

06/26/2020

Site utilities work is continuing, HVAC and electrical work is ongoing in the administration area, and the bus lane is […]

Groundwork

06/12/2020

The concrete grade beams for the new CTE building were placed, and we are installing site utilities in front of […]

DEMO. DEMO. DEMO.

05/29/2020

The demo in the science lab areas is progressing, the asbestos abatement is complete in the locker rooms, and we […]

See You Later Science Labs!

05/22/2020

We’re demoing the existing science labs and pier drilling for the new CTE Building

Demo + Abatement

05/15/2020

We’re continuing to demo in the NE lab area, and we are still in phase 1 of asbestos abatement.

Final Goodbyes

04/20/2020

Goodbye to the old, we’re making room for the new! We have been moving materials and equipment out of phase […]

Weekly Design Meetings Continue

05/07/2019

Procedeo and architect Harrison Kornberg met this week to discuss the scope of work for a new CTE Addition at […]

A look at a new entrance

04/12/2019

Conceptual renderings show a new entrance for O.D. Wyatt High School.

Pre-Proposal Meeting Recap

04/08/2019

A pre-proposal meeting was held for the bid opportunity, RFQ–CMAR 19-093 O.D. Wyatt HS Renovation, where vendors found out more […]

Bid Opportunity & Pre-Proposal Meeting

03/20/2019

Pre-proposal meeting to be held on Wednesday, March 27, 2019 at 10:00 AM for the bid opportunity RFQ – CMAR […]

Student Input and Ideas

10/09/2018

A design charrette was held at O.D. Wyatt High School where students gave their input and design ideas for renovations […]