ADDITION, RENOVATION & FINE ARTS
Amon Carter-Riverside High School
Amon Carter-Riverside High School will receive a new multi-story building to house fine arts, visual arts, media center, science, CTE, JROTC, and Athletics. This addition will create a central campus plaza to the north of the original building.
Work will also include select renovations to the historic 1936 building, relocation of the baseball field, additional student parking, and removal of portable classrooms from the campus.
Fort Worth, TX 76111
EMAIL UPDATES
Subscribe below to receive Amon Carter-Riverside HS email updates.
10/21/2022
To recap, This projects upgrades included major renovations to the historic existing building (originally built in 1936) and a new […]
07/01/2022
Amon Carter-Riverside High School will be ready for students to return this fall! This project includes renovations to the existing […]
06/20/2022
The graphics are being installed
06/03/2022
The entrance is coming together more and more each day!
05/20/2022
The entrance beautification continues!
05/13/2022
The entrance is moving right along!
04/25/2022
Take a look at the progress being made at the entrance!
04/11/2022
The new Amon Carter Media Center is finished!
03/01/2022
01/07/2022
11/17/2021
The handrails in the courtyard and the expansion joint cover in the third floor hallway are being installed
11/08/2021
Amon Carter’s front windows are looking fresh!
11/03/2021
The new interior addition at Amon Carter-Riverside High School is nearly complete and ready to be opened to the students […]
10/13/2021
10/01/2021
Amon Carter-Riverside High School project is making significant project progress on the installation of the new baseball field. The relocation […]
09/13/2021
09/02/2021
The baseball field’s sod has been installed!
08/13/2021
While the renovation part of Amon Carter may be finished, the addition is making great progress!
08/06/2021
The interior and exterior staircases are making progress!
08/02/2021
This historic high school, built in 1936, is receiving 20,000 square feet of renovations and an addition of a new […]
06/11/2021
06/02/2021
The masonry support channel and the steel support decorative metal veil are being painted
04/16/2021
Progress is constantly being made at Amon Carter! The roof and glass are being installed, and the exterior sheathing is […]
04/02/2021
The exterior work is moving along swiftly! Roofing is progressing, as is exterior sheathing, waterproofing, and brickwork
03/12/2021
Demolition has begun on Building E’s outdoor staircase!
03/05/2021
The roof and exterior framing installation is ongoing
02/05/2021
Interior & Exterior framing is making great progress on the new classroom addition!
01/22/2021
Take a look at the progress from a different perspective.
01/20/2021
Framework & ductwork continues even in the early morning!
01/04/2021
The Roof Deck is being installed at the Fine Arts area and the structural steel is being detailed.
12/29/2020
The roof deck at the outdoor learning area and the structural steel is being installed.
12/11/2020
The steel erection for the new classroom building is nearing completion. Take a look from above!
11/13/2020
The third-floor deck is being installed in Areas C & D. Take a look at the progress from this aerial […]
09/18/2020
The structural concrete walls and interior CMU walls are going up
09/04/2020
The structural concrete walls are being placed and the steel erection will begin soon
08/14/2020
The structural walls outside of the athletic area have been poured!
08/07/2020
Looking at Amon Carter from a different angle!
07/24/2020
The tilework continues and the restroom partitions are being installed.
07/17/2020
Two new chillers were set in place by cranes!
07/15/2020
Insulation was added to the air conditioning overhead and site utilities outside the building are being installed underground.
07/10/2020
We were up before the sun to get the first slab poured, and now we’re onto the next pour!
07/03/2020
We started bright and early to get the first section of concrete slabs poured at the new classroom building! The […]
06/26/2020
We’re relocating the AC unit to the rooftop, and installing new chiller pumps and piping in the basement
06/18/2020
We’re laying floor tile as well as beginning assessment for the in-wall plumbing modifications
06/12/2020
The new student parking is nearly complete! All we need is the striping!
06/03/2020
The sod, shrubs, and trees are being planted at the new student parking!
05/29/2020
As the irrigation is being installed in the new parking lot, we began prepping for the new fire lane and the […]
05/22/2020
The excavation around a pier cap for the foundation work is progressing, irrigation is being installed around the new parking […]
05/15/2020
We’re still making great progress here at Carter Riverside! The work is continuing for the foundation grade beams, site utility, […]
05/08/2020
The concrete for the foundation beam has been poured, and we are constructing concrete forms for the foundation grade beam.
05/01/2020
The drive approach to the new student parking was completed last Thursday. The contractor is now focusing on completing installation […]
04/24/2020
The foundation grade beam has been completed in the background (photos 1 & 2), and we are continuing the formwork for […]
04/20/2020
We’re still making great progress over here at Amon Carter Riverside. The new southeast student parking lot has been poured, […]
04/13/2020
We’re not taking our essential work lightly! We’ve been making great progress here at Amon Carter. The underground utility is […]
04/03/2020
We now have soil stabilization for the new student parking area – despite the continual rain! We are still drilling […]
03/20/2020
The city has installed the sewer line extension, and the drilling for auger cast piles (or, the foundation) is at […]
03/06/2020
Even with the rain and a muddy construction site, we’re still making progress! We set up to test the first […]
02/27/2020
Safety is always our #1 priority. We are putting up window protection at the existing building to protect them during […]
02/24/2020
We’ve been working on all things sewers recently. Saw cuts are completed on Gwynne & Yucca for the storm sewer […]
02/13/2020
The stormwater detention system is now complete! We are making great progress on the building pad prep, fencing and prep […]
01/29/2020
It’s as if the new stormwater detention system is attracting more stormwater! But not to worry, we’re still making great […]
01/21/2020
Who would’ve thought a whole baseball field used to be here!? The demo for the baseball field is complete, and […]
12/23/2019
We have a lot planned during winter break for this project! We will be encompassing the baseball field in our […]
11/20/2019
Saying goodbye to the old! Demolition is still progressing, and over the past two weekends, electricians have rerouted some high […]
11/07/2019
Partial demolition has been completed including the old field house, 2 portable buildings and half of Building B.
10/12/2019
Demolition is underway to make room for the new building addition.
09/19/2019
Updated conceptual exterior rendering of the renovations and addition.
08/19/2019
Community members from the neighboring HOAs gathered to learn about the upcoming campus renovations and addition. The complete master plan […]
04/12/2019
Conceptual renderings give a look at the additions to the school from the outside along with the new courtyard for […]
04/11/2019
A pre-proposal meeting was held for the bid opportunity, RFQ-CMAR 19-035 Amon Carter-Riverside HS Addition and Renovation, where vendors found […]
03/29/2019
Pre-proposal meeting to be held on Tuesday, April 2, 2019 at 2:00 PM for the bid opportunity RFQ-CMAR 19-035 Amon […]
11/13/2018
A student design charrette was recently held at Amon Carter-Riverside HS to engage students in the design visioning process for […]